Rankers Hub

Time and work MCQ for all Competitive exams with detailed explanations

MCQ on time and work

4 men can complete a piece of work in 2 days. 4 women can complete the same piece of work in 4 days whereas 5 children can complete the same piece of work in 4 days. If, 2 men, 4 women and 10 children work together, in how many days can the work be completed?

(a) 1 day

(b) 3 days

(c) 2 days

(d) 4 days

(e) None of these


Solution: (a)

4 × 2 men = 4 × 4 women = 5×4 children

\(\displaystyle \Rightarrow \) 2 men = 4 women = 5 children

Therefore, 2 men + 4 women + 10 children

= 20 children

Therefore, latex \displaystyle {{M}_{1}}{{D}_{1}}={{M}_{2}}{{D}_{2}}$

\(\displaystyle \Rightarrow \) 5 × 4 = \(\displaystyle 20\times {{D}_{2}}\) \(\displaystyle \Rightarrow {{D}_{2}}=1day\)

Alternative method

1 man can do the work in 8 days.
1 woman can do the work in 16 days.
1 child can do the work in 20 days.
2m + 4w + 10c can do the work in –
\(\displaystyle \left( {\frac{2}{8}+\frac{4}{{16}}+\frac{{10}}{{20}}} \right)\times \)d = 1
\(\displaystyle \Rightarrow \left( {\frac{1}{4}+\frac{1}{4}+\frac{1}{2}} \right)\times \)d = 1
\(\displaystyle \Rightarrow \)d = 1

Six women and 10 children together take six days to complete a piece of work. How many days will 10 children take to complete the piece of work if six women together can complete the same piece of work in 10 days?

(a) 21

(b) 18

(c) 12

(d) 15

(e) None of these


Solution: (d)

Work done by 6 women in 1 day = \(\displaystyle \frac{1}{{10}}\)

Work done by 6 women in 6 days = \(\displaystyle \frac{6}{{10}}=\frac{3}{5}\)

Therefore, Remaining work = \(\displaystyle (1-\frac{3}{5})=\frac{2}{5}\) which is completed by 10 children in 6 days

Therefore, Work done by 10 children in 1 day = \(\displaystyle \frac{2}{{5\times 6}}=\frac{1}{{15}}\)

Therfore, Time taken in completing the work = 15 days.

Alternate Method:

Number of days required = \(\displaystyle \frac{{6\times 10}}{{10-6}}=\frac{{6\times 10}}{4}=15days\)

2 women and 10 children together take 8 days to complete a piece of work. How many days will 10 children alone take to complete the piece of work if 8 women alone can complete the piece of work in 6 days ?

(a) 15

(b) 12

(c) 10

(d) 24

(e) None of these


Solution: (b)

8 women can do a work in 6 days.

Therefore, 2 women can do same work in = \(\displaystyle \frac{{8\times 6}}{2}=24days\)

2 women can do \(\displaystyle \frac{1}{{24}}\) work in 1 day.

(2 women + 10 children) can do a work in 8 days.

Therefore, (2 women + 10 children)’s 1 days work \(\displaystyle \frac{1}{8}\).

10 Children 1 day work = \(\displaystyle \frac{1}{8}-\frac{1}{{24}}=\frac{1}{{12}}\) work

Hence 10 children can do same work in 12 days.

Alternate method

Consider the speed of work of women as ‘X’ and that of children be ‘Y’ and the Work as ‘W’, then

2X+10Y=W/8 and

8X=W/6

\(\displaystyle \Rightarrow \) X=W/48

Y substituting the value of X in first equation, we get

2(W/48)+10Y=W/8

Y=W/120

\(\displaystyle \Rightarrow \) Speed of 1 Child = W/120

\(\displaystyle \Rightarrow \) Speed of 10 Child = W/12

Hence 10 children can do same work in 12 days.

A and B together can complete a particular task in 8 days. If B alone can complete the same task in 10 days, how many days will A take to complete the task if he works alone ?

(a) 28

(b) 36

(c) 40

(d) 32

(e) None of these


Solution: (c)

Let the A can do the task in x days

\(\displaystyle \frac{1}{x}+\frac{1}{{10}}=\frac{1}{8}\)

\(\displaystyle \frac{1}{x}=\frac{1}{8}-\frac{1}{{10}}=\frac{{10-8}}{{80}}=\frac{2}{{80}}=\frac{1}{{40}}\) 

 X = 40

Alternate Method

If total work = 80 units

Then in 1 day (A+B) will do 80/10 = 10 unit of work

Therefore, A does 2 unit of work each day

Hence, A requires 80/2 = 40 days to complete work

Two pipes can full a tank in 10 h and 16 h respectively. A third pipe can empty the tank in 32 h. If all the three pipes function simultaneously, then in how much time the tank will be full? (in hours)

(a) \(\displaystyle 7\frac{{11}}{{21}}\)

(b) \(\displaystyle 7\frac{{13}}{{21}}\)

(c) \(\displaystyle 8\frac{4}{{21}}\)

(d) \(\displaystyle 6\frac{5}{{14}}\)

(e) \(\displaystyle 8\frac{9}{{14}}\)


Solution: (b)

10 hr A pipe\(\displaystyle \to \)1

16 hr B pipe\(\displaystyle \to \)1

32 hr C pipe\(\displaystyle \to \)1

\(\displaystyle \frac{1}{{10}}+\frac{1}{{16}}-\frac{1}{{32}}=\frac{{21}}{{160}}\)

\(\displaystyle \frac{{160}}{{21}}=7\frac{{13}}{{21}}hr\)

Alternate Method without pen and paper

LCM of 10, 16 and 32 is 160. Therefore,

Units filled by A pipe is 16

Units filled by B pipe is 10

Units filled by B pipe is – 5

If they work together for 1 hour, they will fill (16+10-5) units= 21 units

Time required to fill the tank=\(\displaystyle \frac{{160}}{{21}}=7\frac{{13}}{{21}}hr\)

56 workers can finish a piece of work in 14 days. If the work is to be completed in 8 days, then how many extra workers are required?

(a) 36

(b) 48

(c) 44

(d) 42

(e) 32


Solution: (d)
Here, \(\displaystyle {{M}_{1}}=56,{{D}_{1}}=14,{{M}_{2}}=?,{{D}_{2}}=8\)
Using \(\displaystyle {{M}_{1}}{{D}_{1}}={{M}_{2}}{{D}_{2}}\)
\(\displaystyle 56\times 14={{M}_{2}}\times 8\)
\(\displaystyle {{M}_{2}}=98\)

A alone can make 100 baskets in 6 days and B alone can make 100 baskets in 12 days. In how many days can A and B together make 100 baskets?

(a) 3 days

(b) 5 days

(c) \(\displaystyle 2\frac{1}{2}days\)

(d) \(\displaystyle 3\frac{1}{2}days\)

(e) None of these


Solution: (e)

A’s 1 day’s work = \(\displaystyle \frac{1}{6}\)\(\displaystyle \frac{1}{6}\)

B’s 1 day’s work = \(\displaystyle \frac{1}{{12}}\)

Therefore, (A + B)’s 1 day’s work = \(\displaystyle \frac{1}{6}+\frac{1}{{12}}=\frac{{2+1}}{{12}}=\frac{1}{4}\)

Hence, A and B together will make 100 baskets in 4 days.

Alternate method

A alone can make 100 baskets in 6 days and B alone can make in 12 days.

Therefore, Rate of efficiency of A=100/6 baskets per day

And rate of efficiency of B=100/12 baskets per day

⇒ Baskets made by A and B together in 1 day = \(\displaystyle \frac{{100}}{6}+\frac{{100}}{{12}}=\frac{{300}}{{12}}=25\) baskets per day

Therefore, Time taken by A and B together to make 100 baskets= \(\displaystyle \frac{{100}}{{25}}\)=4 days


Download the Rankers Hub App from the Google play store and start your preparation. Rankers Hub is the best site for online mocks and video courses. Salient features of the courses are we cover all important questions as per the latest pattern, eBooks, previous year’s papers, free mock tests with answers. So, start your preparation with Rankers Hub. Checkout the following courses and test series for competitive exams preparation like SBI POSBI ClerkIBPS POIBPS ClerkIBPS RRBSSC CGLSSC CHSL, and SSC CPO cum defence courses like CDS and AFCAT.

And also, we have best mock test series for Bank exams (SBI POSBI ClerkIBPS POIBPS Clerk, IBPS RRB), SSC Test series like (SSC CGLSSC CHSL, SSC CPO), TSPSC Group 4CDS, and AFCAT are also available. For complete all exams practice mock test check out Rankers Hub website menu bar.