Rankers Hub

ssc cgl time and work questions with solutions

MCQ on Time and Work

Solve the Time and Work Questions check the solutions:

A and B together can do a piece of work in 36 days, B and C together can do it in 24 days. A and C together can do it in 18 days. The three working together can finish the work in

(a) 8 days

(b) 16 days

(c) 30 days

(d) 32 days

(e) 45 days

Answer for this MCQ Time and Work is (b)

(A + B)’s 1 day’s work = \(\displaystyle \frac{1}{{36}}\)

(B + C)’s 1 day’s work =  \(\displaystyle \frac{1}{{24}}\)

(A + C)’s 1 day’s work = \(\displaystyle \frac{1}{{18}}\)

On adding all three,

2 (A + B + C)’s 1 day’s work = \(\displaystyle \frac{1}{{36}}+\frac{1}{{24}}+\frac{1}{{18}}=\frac{{2+3+4}}{{72}}=\frac{9}{{72}}=\frac{1}{8}\)

 (A + B + C)’s 1 day’s work = \(\displaystyle \frac{1}{{16}}\)

Required time = 16 days 

A can do as much work in 4 days as B can do in 5 days, and B can do as much work in 6 days as C in 7 days. In what time will C do a piece of work which A can do in a week ?

(a) \(\displaystyle 10\frac{5}{{24}}days\)

(b) \(\displaystyle 4\frac{4}{5}days\)

(c) \(\displaystyle 6\frac{8}{{15}}days\)

(d) \(\displaystyle 12\frac{6}{{19}}days\)

(e) \(\displaystyle 16\frac{5}{9}days\)

Answer for this MCQ Time and Work is (a)

A’s 4 days’ work = B’s 5 days’ work

\(\displaystyle \Rightarrow \) A : B = 4 : 5

Again, B : C = 6 : 7

Therefore,

A : B : C = 4 × 6 : 5 × 6 : 5 × 7 = 24 : 30 : 35

 Time taken by A = 7 days

Hence, Time taken by C = \(\displaystyle \frac{{35}}{{24}}\times 7=\frac{{245}}{{24}}=10\frac{5}{{24}}days\)

A can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days. In how many days will A, B and C finish it, working all together?

(a) 6 days

(b) \(\displaystyle 5\frac{1}{4}days\)

(c) \(\displaystyle 4\frac{4}{{11}}days\)

(d) 4 days

(e) 11 days

Answer for this MCQ Time and Work is (d)

A’s 1 day’s work = \(\displaystyle \frac{1}{{10}}\)

B’s 1 day’s work = \(\displaystyle \frac{1}{{12}}\)

C’s 1 day’s work = \(\displaystyle \frac{1}{{15}}\)

Therefore,

 (A + B + C)’s 1 day’s work = \(\displaystyle \frac{1}{{10}}+\frac{1}{{12}}+\frac{1}{{15}}=\frac{{6+5+4}}{{60}}=\frac{{15}}{{60}}=\frac{1}{4}\)

Required time = 4 days.

A and B can do a piece of work in 72 days. B and C can do it in 120 days and A and C can do it in 90 days. A alone can do it in :

(a) 120 days

(b) 130 days

(c) 150 days

(d) 100 days

(e) 180 days

Answer for this MCQ Time and Work is (a)

(A + B)’s 1 day’s work = \(\displaystyle \frac{1}{{72}}\)

(B + C)’s 1 day’s work = \(\displaystyle \frac{1}{{120}}\)

(C + A)’s 1 day’s work  = \(\displaystyle \frac{1}{{90}}\)

On adding all three,

2 (A + B + C)’s 1 day’s work = \(\displaystyle \frac{1}{{72}}+\frac{1}{{120}}+\frac{1}{{90}}=\frac{{5+3+4}}{{360}}=\frac{{12}}{{360}}=\frac{1}{{30}}\)

Therefore,

(A + B + C)’s 1 day’s work = \(\displaystyle \frac{1}{{60}}\)

A’s 1 day’s work = Equation (iv) – (ii),

= \(\displaystyle \frac{1}{{60}}-\frac{1}{{120}}=\frac{{2-1}}{{120}}=\frac{1}{{120}}\)

The required time = 120 days

A and B can do a work in 18 and 24 days respectively. They worked together for 8 days and then A left. The remaining work was finished by B in :

(a) 5 days

(b) \(\displaystyle 5\frac{1}{3}\) days

(c) \(\displaystyle 8\frac{3}{5}\) days

(d) \(\displaystyle 10\frac{1}{5}\) days

(e) 15 days

Answer for this MCQ Time and Work is (b)

A can finish the work in 18 days.

Therefore, A’s one day’s’ work = \(\displaystyle \frac{1}{{18}}\)

Similarly, B’s one day’s work = \(\displaystyle \frac{1}{{24}}\)

(A + B)’s 8 days’ work = \(\displaystyle (\frac{1}{{18}}+\frac{1}{{24}})\times 8=\frac{7}{{72}}\times 8=\frac{7}{9}\)

Therefore, Remaining work = \(\displaystyle 1-\frac{7}{9}=\frac{2}{9}\)

Hence, Time taken to finish the remaining work by B is \(\displaystyle \frac{2}{9}\times 24=\frac{{16}}{3}=5\frac{1}{3}days\)

Alternate Method :

Here, m = 18, n= 24 and p = 8

\(\displaystyle \Rightarrow \) Required Time = \(\displaystyle \frac{{8\times 24-8(8+24)}}{{18}}\)

\(\displaystyle \frac{{432+336}}{{18}}=\frac{{96}}{{18}}=\frac{{16}}{3}=5\frac{1}{3}days\)

A can do a piece of work in 12 days and B can do it in 18 days. They work together for 2 days and then A leaves. How long will B take to finish the remaining work ?

(a) 6 days

(b) 8 days

(c) 10 days

(d) 13 days

(e) 15 days

Answer for this MCQ Time and Work is (d)

(A+B)’s 2 days’ work = \(\displaystyle 2(\frac{1}{{12}}+\frac{1}{{18}})=\frac{{10}}{{36}}\)

Remaining work = \(\displaystyle 1-\frac{{10}}{{36}}=\frac{{26}}{{36}}\)

Time taken by B to complete \(\displaystyle \frac{{26}}{{36}}\) part of work

Alternate Method :

Here, m = 12, n = 18, p = 2

Time taken by B

\(\displaystyle \frac{{mn-p(m+n)}}{m}=\frac{{12\times 18-2(12+18)}}{{12}}\)

\(\displaystyle \frac{{216-60}}{{12}}=13days\)

A and B can do a piece of work in 28 and 35 days respectively. They began to work together but A leaves after sometime and B completed remaining work in 17 days. After how many days did A leave ?

(a) \(\displaystyle 14\frac{2}{5}\) days

(b) 9 days

(c) 8 days

(d) \(\displaystyle 7\frac{5}{9}\) days

(e) 20 days

Answer for this MCQ Time and Work is (c)

Let A worked for x days.

According to question

\(\displaystyle \frac{x}{{28}}+\frac{{(x+17)}}{{35}}=1\)

\(\displaystyle \frac{{5x+4(x+17)}}{{140}}=1\)

5x + 4x + 68 = 140

9x = 140 – 68 = 72

x = 8

Therefore, A worked for 8 days

A and B together can complete a work in 8 days. B alone can complete that work in 12 days. B alone worked for four days. After that how long will A alone take to complete the work ?

(a) 15 days

(b) 18 days

(c) 16 days

(d) 20 days

(e) 25 days

Answer for this MCQ Time and Work is (c)

Time taken by A = \(\displaystyle \frac{{8\times 12}}{4}=24days\)

Work done of by B = \(\displaystyle \frac{4}{{12}}=\frac{1}{3}\)

Remaining work = \(\displaystyle 1-\frac{1}{3}=\frac{2}{3}\)

A can complete a work in 24 days

A can complete \(\displaystyle \frac{2}{3}\)  part of work in 16 days